You can use Work Environment configuration
in the Project Area editor to specify the hours per day and days per week
for a project. These settings are used to determine work durations in iteration
planning and work item interfaces. Team members can customize their own work
schedules on the Work Environment page of the User editor.
To set project hours and days per week:
- Right-click the project area in the Team Artifacts view
and click Open. The project area opens in the editor
view.
- Click the Process Configuration tab.
- In the Project Configuration section, expand
the Configuration Data and Iteration Plans sections.
- Click the Work Environment node.
- Set the Work Hours per Day and Work
Days per Week, and click Save.